Tuesday, September 8, 2015

NSF Notifications and Requests (Fastlane vs. Research.gov)

In a previous post, we discussed the various Award Recipient Responsibilities that required either advanced notification to or prior approval from the NSF.

"Notifications and requests communicate changes in the scope, time, staff or budget of an NSF funded project. Depending on the type of change, awardee organizations must notify or request approval from NSF prior to taking action."

Please take a moment to familiarize yourself with the various types of notifications and requests.

The purpose of this post is to draw your attention to the fact that, "As part of the effort to modernize FastLane, the National Science Foundation is transitioning the notifications and requests functionality from FastLane to Research.gov. The table below provides the location for each notification and request."

You can use your NSF Login Credentials to access Research.gov.


TypeNotification or RequestPolicy Reference  Location
Budget Activities
Additional categories of participant support costs other than those described in 2 CFR § 200.75 (such as incentives, gifts, souvenirs, t-shirts and/or memorabilia) Request GPG (II.C.2.g(v)) Research.gov
Change in Person-Months Devoted to Project


Request AAG (II.B.2.d) Research.gov
Pre-award Costs in Excess of 90 days Request AAG (V.A.2.b) Research.gov
Reallocation of Funds Provided for Participant Support Costs Request GPG (II.C.2.g(v)) Research.gov
Rearrangements/Alterations in excess of $25,000 (Construction) Request AAG (V.C.1) Research.gov
Salaries of Administrative or Clerical Staff Request GPG (II.C.2.g(i)(b)) Research.gov
Travel Costs for Dependents Request GPG (II.C.2.g(iv)(a)) Research.gov
No-Cost Extension
Grantee-Approved No-Cost Extension Notification AAG (I.D.3.c(i))


FastLane
First NSF-Approved No-Cost Extension        Request AAG (I.D.3.c(ii)(a) FastLane
Second NSF-Approved No-Cost Extension Request AAG (I.D.3.c(ii)(b)) FastLane
Changes in Objectives, Scope, or Methodology or other Significant Changes
Changes in Objectives or Scope Request AAG (II.B.1.a) Research.gov
Significant Changes/Delays or Events of Unusual Interest Notification AAG (II.B.1.c) Research.gov
Significant Changes in Methods/Procedures Notification AAG (II.B.1.b) Research.gov
Changes in PI/PD and co-PI/PD
Long-Term Disengagement of the PI/Project Director (PD) or co-PI/co-PD Request AAG (II.B.2.c) Research.gov
PI/PD or co-PI/co-PD Transfer from one organization to another Request AAG (II.B.2.g) FastLane
Substitute PI/PD or co-PI/co-PD Request AAG (II.B.2.f) FastLane
Withdrawal of PI/PD or co-PI/co-PD Request AAG (II.B.2.e) Research.gov
Other
Annual and Final Cost Share Notification by Recipient Notification AAG (II.D.5) FastLane
Conflicts of Interest that cannot be satisfactorily managed, reduced or eliminated and research that proceeds without the imposition of conditions or restrictions when a conflict of interest exists Notification AAG (IV.A)

Research.gov
Subawarding, Transferring or Contracting Out Part of an NSF Award Request GPG (II.C.2.g(vi)(e))
AAG (II.B.3)
FastLane

No comments: